Project Update December 2025

The Tasway Energy Park team wished to give an update following the release of Gate 1 grid connections offers from the National Energy System Operator (NESO). 

NESO has been undertaking reform of the queue for grid connections across the country. Tasway Energy Park submitted an application to NESO this summer and the outcome of that process is now known. 

Tasway Energy Park has been awarded a Gate 1 offer. This means when capacity becomes available in the region we would be eligible to accept a full grid connection offer.  

The project team will now be reviewing next steps for the Tasway programme and how this outcome will affect this. This outcome will mean there will be a delay to the planning submission process until the project has better visibility of a grid connection point.  

In the meantime, we remain contactable via the below contact details and our project website will remain available with all information and materials from our Phase 1 consultation. We will also post any further updates on the website.  